CONSTRUCTION OF MBERA RESOUCE CENTRE CLASS ROOM BLOCK AND 2 VIP PITLATRINE TOILETS

IMPROVING ACCESS TO INFORMATION

Start date: 2021-12-13 Due date: 2022-08-30 Approval date: 2022-03-16 Green Category (0 Red Flags)
27,931,635.00   MWK
Total Budget
2022-08-17
Date Created
2025-08-15
Last updated
Construction
Project Type
Decommissioning
Project Status

Locations

Description STA Mbera
District Balaka
Region Southern
Street address Balaka North Constituency, Liwawazi Ward
Postal code

Documents

Title Social and Environmental impact Report
Description Social and Environmental impact Report
Document Type Social impact assessment
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Site Environmental Management Report
Description GESD and DDF projects Site Environmental Management Report
Document Type Environmental Impact
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Technical appraisal report
Description Site Technical appraisal report
Document Type Feasibility study
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Technical Appraisal
Description Assessment of potential benefits of the construction project to community
Document Type Cost-benefit analysis
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Maintence Plan
Description Maintenance plan for buildings
Document Type Maintenance Plan
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

No records were added

Contracts

OCID BDC/IPDC/RFQ/GESD 2021-2022/06
External Reference
Title Mbera Youth Resource Centre Contract details
Description Mbera Youth Resource Centre Contract details
Status Closed
Contract Value MWK 27,931,615.00
Cost Estimate MWK 27,931,635.00
Final Value 0.00
Start Date 2022-01-05
End Date 2022-03-22
Max Extent Date 2022-09-05
Duration In Days 243
Procurement Method Open
Method Details Best value to government
Procuring Entity Balaka District Council-Balaka-MW
Administrative Balaka District Council-Balaka-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2022-04-30
End Details: the project was completed within the implementation period
Final Scope: Completed according to scope
Final Scope Details: Main building and two toilets were all completed according to scope
Final Value Amount: MWK 27,931,635.00
Final Value Details: Completed without additional costs

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

Land compensation budget 0.00
In indigenous land FALSE

Meetings

Street Address Mbera site
Locality TA Kachenga
Region South
Country Code Malawi
Date 2022-08-18
Number of Participants 8

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-09-01
End Date 2052-12-27
Max End Date 2062-08-25