Construction of 30 tonne concrete deck bridge at Mtambwa on Mudi river ,T/A Khongoni


construction of a 30 tonne capacity deck bridge

to improve the quality of transportation of motorised and non motorised traffic across water bodies

Start date: 2024-08-12 Due date: 2025-04-10 Approval date: 2023-03-06 Orange Category (8 Red Flags)
Lack of supporting feasibility study Lack of environmental impact assessment Lack of social Impact assessment Lack of cost benefit analysis Public consultation meetings not held Limited competition Project delays Lack of maintenance plans
100,000,000.00   MWK
Total Budget
2025-03-14
Date Created
2025-03-14
Last updated
Construction
Project Type
Implementation
Project Status