Installation of Usingini-Usisya water pipe line


The project was meant to improve safe , potable and hygiene water accessibility among households in Usisya

To promote accessibility to safe, potable and hygiene water accessibility among households in Usisya

Start date: 2023-01-14 Due date: 2023-06-14 Approval date: 2022-04-01 Orange Category (7 Red Flags)
Lack of supporting feasibility study Lack of environmental impact assessment Lack of social Impact assessment Lack of cost benefit analysis Public consultation meetings not held Limited competition Lack of maintenance plans
35,237,075.00   MWK
Total Budget
2023-06-05
Date Created
2023-06-05
Last updated
Expansion
Project Type
Not Set
Project Status

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;