image

Installation of Usingini-Usisya water pipe line


The project was meant to improve safe , potable and hygiene water accessibility among households in Usisya

To promote accessibility to safe, potable and hygiene water accessibility among households in Usisya

Start date: 2023-01-14 Due date: 2023-06-14 Approval date: 2022-04-01 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
35,237,075.00   MWK
Total Budget
2023-06-05
Date Created
2023-06-05
Last updated
Expansion
Project Type
Not Set
Project Status

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.