image

ROAD RESHAPING FROM MIKAYA'S RESIDENCE TO JEHOVAH'S WITNESS CHURCH


The project involved forming a road camber and drainage systems using labour intensive

To improve accessibility within the ward

Start date: 2022-07-06 Due date: 2024-03-31 Approval date: 2022-07-01 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
1,000,000.00   MWK
Total Budget
2023-05-18
Date Created
2023-05-18
Last updated
Construction
Project Type
Completion
Project Status

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;