CONSTRUCTION OF MPHIKA SCHOOL BLOCK


The project will involve construction of a primary school block. It will involve a complete double classroom block and furniture.

The project aims at addressing very high enrolment rates.

Start date: 2023-01-10 Due date: 2023-09-30 Approval date: 2023-01-10 Orange Category (8 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Frequent project delays (time overruns) Lack of maintenance plans
26,680,120.00   MWK
Total Budget
2023-05-17
Date Created
2023-05-20
Last updated
Construction
Project Type
Implementation
Project Status