Construction of Staff House at Mwenilondo Health Centre

        Return back Please wait...
image

Construction of Staff House at Mwenilondo Health Centre

The works involve construction of a 3 bed room house with flush toilet, kitchen and stores apartments

The purpose is to provide housing accommodation to Health Worker working at the Health facility.

Start date: 2021-10-15 Due date: 2022-01-13
2,194,735,050.00   MWK
Total Funding
2021-07-01
Approval date
2023-06-02
Last updated
construction
Project Type
completed
Project Status

Locations

DESCRIPTION DISTRICT REGION ADDRESS
Mwenilondo Health Centre Karonga Northern Mwenilondo Trading Centre

completion