UPGRADING OF NSANAMA-NAYUCHI ROAD (MOZAMBIQUE BORDER) -T393
Roads Authority | updated on November 16, 2021
About this project
The Nsanama-Nayuchi/Mozambique Border Road section is approximately 44 km long with very sandy soils. The road starts at Nsanama and ends at Nayuchi on the Mozambique border. It passes through two trading centres, namely Mbanila and Namanja. The scope of works under this project is the upgrading of 10km of road section from Nsanama to Nkhande Bridge towards Nayuchi.The works will include construction of a 6.7m wide carriageway and 1.5m wide sealed shoulders on each side of the road. The pavement layers will be constructed from natural gravels with 50mm Asphalt Concrete surfacing.
Flags 8 Flags
Property Highlights
Total Budget (MWK)
MWK 5,361,576,130.35
Project Type
construction
Project Status
implementation
Start Date
April 23, 2021
Due Date
February 22, 2022
Aprroval Date
July 1, 2019

Last updated on November 16, 2021

Project Details
All View all project information in all phases or stages
Identification View project information on the identification stage
Preparation View project information on the preparation stage
Tendering View project information on the tendering stage
Implementation View project information on the implementation stage
Completion View project information on the completion stage
Maintenance View project information on the maintenance stage
Decommissioning View project information on the decommissioning stage
Location
Discover where Our projects Are located
Parties
Discover All Associated Parties
Documents
Discover All Project Documents
Contracts
View All Project Contracts
Budgets
Discover All Budgets of the project
Transactions
Discover All Transactions of the project
Benefits
Discover All Project Benefits
Social
Discover All Project Social Information
Environment
Discover All Project Environments
Metrics
Discover All Project Metrics
Milestones
Discover all project milestones
Completion
View all completion information
Feedback's

Showing 30 feedback comments