Project

Construction of security institutional houses for Malawi Police Services at IPYANA and SONGWE in karonga district

image

Construction of security institutional houses for Malawi Police Services at IPYANA and SONGWE in karonga district


construction of houses and its associated works

To provide secure institutional houses for the police service

Start date: 2020-11-30 Due date: 2022-06-30 Approval date: 2020-03-10 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
1,300,795,693.88   MWK
Total Budget
2023-04-03
Date Created
2023-04-14
Last updated
Construction
Project Type
Completion
Project Status