CONSTRUCTION OF AREA 18B NORTHREN FOOTBRIDGE UNDER CONSTITUENCY DEVELOPMENT FUND (CDF) IN LILONGWE CITY CONSTITUENCY-LOT3

image

CONSTRUCTION OF AREA 18B NORTHREN FOOTBRIDGE UNDER CONSTITUENCY DEVELOPMENT FUND (CDF) IN LILONGWE CITY CONSTITUENCY-LOT3


CONSTRUCTION OF 8m long AREA 18B NORTHREN CONCRETE FOOTBRIDGE UNDER CONSTITUENCY DEVELOPMENT FUND (CDF) IN LILONGWE CITY CONSTITUENCY-LOT3

Improve transportation of goods and services from area 18A to area 18B

Start date: 2022-11-14 Due date: 2023-01-31 Approval date: 2022-04-01 Orange Category (7 Red Flags)
Lack of supporting feasibility study Lack of environmental impact assessment Lack of social Impact assessment Lack of cost benefit analysis Public consultation meetings not held Limited competition Lack of maintenance plans
26,406,446.99   MWK
Total Budget
2023-01-10
Date Created
2023-04-04
Last updated
Construction
Project Type
Completion
Project Status