Project

DRILLING OF EIGHT BOREHOLES IN LILONGWE CITY WEST CONSTITUENCY

        Return back Please wait...
image

DRILLING OF EIGHT BOREHOLES IN LILONGWE CITY WEST CONSTITUENCY

Drilling of eight boreholes in lilongwe city west constituency

Providing safe water to the community and easy accessibility of water to the community.

Start date: 2022-06-22 Due date: 2022-11-24
29,028,616.48   MWK
Total Funding
2022-04-30
Approval date
2023-01-10
Last updated
construction
Project Type
completed
Project Status

Locations

DESCRIPTION DISTRICT REGION ADDRESS
Lilongwe city west(Mtandire) Lilongwe Central P.o Box 30396

completion






© 2024, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.