image

masaf culvert installation under constituency development fund


masaf culvert installation under constituency development fund in area 49

improve drainage in lilongwe city, for easy crossing of cars and people

Start date: 2022-06-04 Due date: 2022-08-16 Approval date: 2022-04-30 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
18,603,347.00   MWK
Total Budget
2022-08-26
Date Created
2022-08-26
Last updated
Construction
Project Type
Completion
Project Status